Location
Myingyan, Myanmar
Start date
January 2015
Duration
3 Months
Volume
250 Containers
Contract Value
500,000 USD
Equipment/Services used
Customs clearance
Inland road transport
Inland water transport
Air freight
Drawback cargo solution
Tugboat
Barge
Transformers
Mobile cranes
Multi-axle hydraulic trailer
Cherry picker
Generator 3 Phase
CEA Myanmar was contracted for customs clearance and transportation to aid in the construction of a temporary power plant which had to be commissioned within 60 days of the first containers arriving in Myanmar.
CEA’s scope of work was to provide transportation for 250 Shipper Owned and Carrier Owned Containers (SOC & COC) from central Yangon, 560km inland to the Myingyan district, approximately 100km south of Mandalay.
The power plant when competed will be able to produce 95 megawatts of power and will stay in operation for two years before being decommissioned with 70 percent of the materials being exported again for future use.
Along with providing inland road & water transport, CEA Myanmar supplied 2 x 55 tonne 132Kv transformers, that were shipped by barge to the Myingyan district and then transported 30km to the power plant site by Multi-Axle Hydraulic Trailer. CEA also organised the mobilisation of a 70-tonne rough terrain crane transported by barge along the Ayeryawaddy River to the construction site.
The power plant configuration is 31 generators and their accompanying cooling units per line, with three in-line transformers to step up the voltage before transferring the generated power to the site substation and then into the national grid. This will provide enough power to supply over 500,000 homes throughout the region
The 12-day journey via the Ayeryawaddy River was necessary due to transport weight restrictions by the Burmese land transport department. This proved to be a more cost-effective mode of transport for the client. Onsite operations included a lifting plan for the transformers using a 220-tonne crane and a 70-tonne crane for use with the generators, inline transformers and general cargo. CEA Myanmar will continue the project throughout with the shipping of spares and other equipment for the duration of the operations.
To download the case study Click Here
Click to learn more about CEA Heavy Lift and Heavy Transport services