CEA Project Logistics Technical Lifting

Technical Lifting

Location
Laem Chabang Port, Thailand

Duration 
2 Days

Number of carriages
6

Destination
BTS HQ Bangkok

CEA Project Logistics Technical Lifting - CEA Reach Stacker
Specialised lifting clamps attached

CEA Project Logistics Technical Lifting - Clamp
Precision lifting points

CEA Project Logistics Technical Lifting - Carriage lashed in place
Carriages secured with ratchet straps

CEA Project Logistics were required to perform a technical lift and the loading of six BTS train carriages that were to be transported to the BTS headquarters in Bangkok.

Procedure

Two CEA Project Logistics reach stackers fitted with specialised clamps lifted each carriage from their bogies. Hydraulic multi-axle trailers were moved into position beneath, each carriage was lowered with precision into their respective slots on the trailers. The CEA rigging team secured the carriages in place with ratchet straps and wooden chocks readying the carriages for transportation.

CEA PROVIDED

  • Manpower
  • Reach stackers (2)
  • Rigging equipment
  • Wooden chocks
  • Hiab crane
  • Forklift (7t)
  • Hydraulic trailer

To download the case study Click Here